Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To agree additional capital expenditure for the Museum re-development project due to the uplift in the main building contract price.
(1) That the 6% uplift in the cost of works associated with the District Museum redevelopment due to unforeseen delays, additional building works and associated professional fees be noted; and
(2) That the recommendations within the separate report on the Capital Programme in respect of the budget for this issue be noted.
Report author: Julie Chandler
Publication date: 10/12/2015
Date of decision: 03/12/2015
Decided at meeting: 03/12/2015 - Cabinet
Effective from: 18/12/2015