Epping Forest Operations Hub
(Contracts, Service Delivery and Improvement – Cllr R Balcombe) To approve the contractor for the design and build of the Operations Hub and agree the budget recommendation (C-053-2023-24).
Additional documents:
Decision:
(1) That the Cabinet approved the appointment of Barnes Construction for the design and build of the Operations Hub at North Weald Airfield.
(2) That the Cabinet recommended to Council the inclusion of a maximum additional £1,733,000 allocation within the capital programme for construction of Operations Hub at North Weald Airfield.
Minutes:
It was noted this item was considered in private session. The report set out the options considered, if any, and the reasons for the recommendation and the decision.
Decision:
(1) That the Cabinet approved the appointment of Barnes Construction for the design and build of the Operations Hub at North Weald Airfield.
(2) That the Cabinet recommended to Council the inclusion of a maximum additional £1,733,000 allocation within the capital programme for construction of Operations Hub at North Weald Airfield.