Agenda item

Progress Report - Phases 2-4

To consider the attached report (CHB-001-2020/21).

Decision:

(1)             That the contents of the Progress Report on Phases 2 to 4 of the Council House Building Programme be noted and presented to Cabinet in line with the Terms of Reference of the Council Housebuilding Cabinet Committee.

Minutes:

Deborah Fenton, Service Manager, Housing Management and Home Ownership, presented a report to the Cabinet Committee, she advised that the report set out the progress that has been made across phases 2 to 4 of the Council Housebuilding programme that had either been completed, were on-site or were currently being procured.

 

Phase 2 – Burton Road, Loughton

 

Burton Road, Loughton consisted of 51 properties, 15 x 3 Bed Houses, 2 x 2 Bed Houses, 23 x 2 Bed Flats and 11 x 1 Bed Flats.

 

There was a delay in the handover of the remaining 6 properties which occurred on the 19 March 2020, this delay was due to a gas supply issue. There remained a 2.5% retention of £271,899.

 

Phase 3 – Queens Road, North Weald

 

Queens Road, North Weald consisted of 12 properties, 10 x 3 Bed Houses and 2 x 2 Bed Houses. The original start date was delayed due to the discovery of asbestos and a new road and sub-station works. This was currently forecast to be completed on the 30 September 2020 however, further delay was anticipated due to the Covid-19 restrictions upon the supply chain.

 

Phase 4.1

 

There were 14 units in phase 4.1 that had been tendered and were approved at the Council Housebuilding Cabinet Committee on 19 December 2019, contracts had been signed and the start on site dates were as below.

 

 

 

 

Latest Anticipated Start on Site

Handover

Chequers Road (A), Loughton

HR 124

3 x units

29:06:20

29:06:21

Bushfields, Loughton

HR 122

2 x units

29:06:20

29:06:21

Chester Road, Loughton

HR 130

3 x units

03:08:20

29:06:21

Queensway,

Ongar

HR 140

4 x units

07:09:20

29:06:21

Millfield,

Ongar

HR 138

2 x units

07:09:20

29:06:21

Total

 

14 x units

 

 

 

Contracts had been signed and the pre-design work had continued to be progressed within the Government Guidelines and restrictions, with the aim of minimising any delay to the commencement of works on site. A staggered start on site was to be made to assist with compliance with the new Covid-19 working arrangements, notwithstanding that it was currently anticipated that all handovers would occur by the end of June 2021.

 

Phase 4.2

 

There were 22 units that had been tendered and an update would be reported to the Council Housebuilding Cabinet Committee meeting on the 8 September 2020.

 

 

 

 

Latest Anticipated Start on Site

Handover

Hornbeam Road (B), Buckhurst Hill

HR 136

3 x units

12.07:20

12.07:21

Hornbeam House, Buckhurst Hill

HR 137

2 x units

12.07:20

12.07:21

Bourne House, Buckhurst Hill

HR 135

2 x units

12.07:20

12.07:21

Etheridge Road, Debden

HR 127

3 x units

12.07:20

12.08:21

Denny Avenue, Waltham Abbey

HR 144

3 x units

12.07:20

12.08:21

Beechfield Walk, Waltham Abbey

HR 147

5 x units

12.07:20

12.08:21

Kirby Close, Loughton

HR 120

4 x units

12.07:20

12.08:21

Total

 

22 x units

 

 

 

Subject to the acceptance by the Cabinet of this the latest anticipated Start on Site and Handover dates which are given above.

 

Phase 4.3

 

There were 21 units being progressed for tender and a further report updated report would come to 8 September 2020 meeting of the Council Housebuilding Cabinet Committee.

 

Pick Hill, Waltham Abbey

HR 145

2 x units

Pentlow Way, Buckhurst Hill

HR 139

7 x units

Bromefield Court, Waltham Abbey

HR 143

1 x units

Bromefield Court, Waltham Abbey

HR 147

1 x units

Stoneyshotts, Waltham Abbey

HR 148

1 x units

Woollard Street, Waltham Abbey

HR 149

8 x units

Wrangley Court, Waltham Abbey

HR 161

1 x units

Total

 

22 x units

 

These sites were anticipated to be issued for tender by the end of June 2020 with the aim of making a Start on Site in November 2020 and Handover by November 2021/March 2022.

Notwithstanding the current Government restrictions there had been good progress made in these difficult circumstances to continue to progress due diligence and work towards completing the design to minimise any further potential delays.

Phase 4.4

 

There were 27 units (including an additional 12 units) which were being technically progressed in anticipation of planning submission and tender.  

 

Chequers Road (B), Loughton

8 x units

Ladyfields, Loughton

16 x units

Lower Alderton Hall Lane, Loughton

2 x units

Thatchers Close, Loughton

1 x units

Total

27 x units

 

The table above now reflected a potential increase in affordable units of 12 over what had previously been forecast and approved.

 

Phase 5

 

A detailed review was nearing conclusion to identify several potential sites which may be progressed for future development. This would involve engagement with Local Councillors to discuss and address local issues so that these development sites may progress.

 

Once these have progressed sufficiently and have been initially assessed, a Feasibility Report would be presented to Cabinet for consent to proceed and progress to the planning application and delivery stage.

 

The Rights of Way/Access issues stemming from the Appropriation process were being addressed in line with the phased programme. A policy is being developed to ensure a fair and consistent approach was being taken.

 

Councillor A Patel asked in there had been any increase in the cost of the construction and materials post covid-19.

 

John Cosgrave, Interim Housing Development Manager advised that the contractual position was that they could claim an extension of time but they could not claim any additional prelims. Presently there were no indications of any potential increase in costs associated with materials.

 

Councillor A Patel asked in terms of the 12 weeks lost due to the Covid-19 lockdown, if the Contractors were unable to complete on the May deadline, should we be negotiating with them now for a contract extension to take this period of time into account.

 

The Interim Housing Development Manager replied the delay over the last 12 weeks had partially been factored in. As this contract was a predominantly design and build contract there was an obligation on them to carry out certain design work, which fortunately coincided with the Covid-19 lockdown period.

 

There had been a delay identified in Phase 2, Queens Road where the contract had been due to finish in August 2020 but was now currently running 8 weeks late. The cost associated with that was not anticipated to be excessive, the main for the delay, which were cost related would be due to third party services which have not yet been quantified. These costs associated with the delay are not anticipated to be materially excessive as to what would be reasonable.

 

Councillor J Philip stated with regard to Phase 4.2 which was supposed to start on site in July this year, the planning permissions were agreed three or four years ago with a commencement start date within three years of approval. Therefore most of the planning permissions would now have expired, so how could a start on site in July be implemented if the planning permissions had expired, new planning permissions would have to be sought, which would now be caught by the Special Area of Conservation (SAC).

 

The Interim Housing Development Manager advised that the planning consents were enacted within the time limit. The pre-commencement conditions, in terms of carrying out certain demolition works and contamination surveys, were commenced and signed off so the planning consents were enacted.

 

Councillor J Philip stated that normally a pre-commencement condition happened before you would commence on site, the commencement of the planning condition happens after you have removed the pre-commence condition.

 

The Interim Housing Development Manager advised that the pre-commencement that related to the planning consents had been activated in time and therefore the planning consents had been maintained except for Thatchers Close and Lower Alderton Hall Drive.

 

Councillor N Bedford asked with regard to Phase 4.1, Queensway and Millfield, Ongar are they scheduled to start on the 7 September 2020 or will there be a delay with regard to the Covid-19 lockdown.

 

The Interim Housing Development Manager advised that there had been a recent meeting with the contractor and Queensway and Millfield were currently on track to start on the 7 September, the contractor will notify the Council as soon as possible to any anticipated delays.

 

Councillor N Bedford asked how much was the contingency allowance and should more funds be factored in. On previous sites it was found that when we have hit a contingency its wasn’t budgeted correctly, there was an massive overspend on the sites due to asbestos which was found below the sites and these sites are exactly the same sort of garage sites.

 

The Interim Housing Development Manager advised in terms of contingency I am aware that on previous phases there had been a considerable cost increase experience, due to a number of different factors, a great deal of those issues had been mitigated by the process adopted on Phase 4. In terms of forecasting for contingency we have identified that circa 10% of the construction cost was adequate.

 

Councillor Patel highlighted a paragraph in the report on agenda page 15:

 

Also of note in response to the Councils Climate Emergency pledge on 19th September 2019, “to do everything within the Councils power to make Epping Forest District Council area carbon neutral by 2030” we are currently carrying out a review of the construction proposals with the aim of moving closer to achieving a ‘Passivehaus’ standard by incorporating the ‘Passivehaus’ principals within the massing and fabric design which will go a great way towards achieving the Councils stated aim.”

 

Councillor Patel stated that he welcomed that paragraph and that as a Committee, supported that move forward.

 

The Chairman, Councillor H Whitbread advised that the Burton Road development was a very eco-friendly development with smart readers and solar panels and that would help the Council along the way to the net zero target.

 

Councillor Morgan asked if there was an update to the garages at the Colvers in Matching Green as in the past there had been talk of the site becoming demolished and houses built on it.

 

The Interim Housing Development Manager advised that the application was refused at committee and due to the Council reorganisation, the garage uses are currently being assessed under the new structuring plan as different people are now responsible for dealing with the functions of managing the garages.

 

Councillor C C Pond advised that now the Burton Road site was completed he had a number of representations from people who have moved into the Burton Road development asking about parking. Although tenants were told at the beginning that there was none or very limited parking they have requested, through Councillor Avey’s team, that season tickets be made available in the Burton Road car park, which is opposite the development, where the residents say that it is very seldom under any stress. Therefore could the Chairman and Councillor Avey meet to see if any scheme could be devised to allow those people to acquire season tickets in the Burton Road car park while there is still capacity in them.

 

The Service Manager, Housing Management and Home Ownership advised that Torrington Drive, which runs behind Burton Road had some designated parking and the Housing team are looking to see if any of that space could be utilised by the residents in Burton Road. She advised that she would report back the findings at the next meeting.

 

The Chairman thanked Officers for their continued work on the Burton Road development and advised that at the beginning of the Covid-19 lockdown the opening of Burton Road development was due to go ahead but this had to be cancelled, which was very disappointing. She advised that before the lockdown she did get to visit the site with the local MP who was very impressed with the buildings and hopefully this can be marked when the social distancing has been lifted.

 

Decision:

 

(1)             That the contents of the Progress Report on Phases 2 to 4 of the Council House Building Programme be noted and presented to Cabinet in line with the Terms of Reference of the Council Housebuilding Cabinet Committee.

 

Reasons for the Decision:

 

Set out in its Terms of Reference, the Council Housebuilding Cabinet Committee is to monitor and report to the Council on an annual basis on progress and expenditure concerning the Council House Building Programme. This report sets out the progress made over the last 12 months.

 

Other Options Considered and Rejected

 

This report is on the progress made over the last 12 months and is for noting purposes only. There are no other options for action.