Agenda item

Planning Application - EPF/0504/21 Purlieu House, 11 Station Road, Epping CM16 4HA

To consider the attached report for an additional storey to facilitate the creation of six flats and change of use of part ground from B1 office to retail for the building to comprise of a retail unit on the ground floor and retained under croft parking, offices to first floor, and the flats on the second and newly created third floor.

Minutes:

APPLICATION No:

EPF/0504/21

 

SITE ADDRESS:

Purlieu House

11 Station Road

Epping

CM16 4HA

 

PARISH:

Epping

 

WARD:

Epping Hemnall

 

 

DESCRIPTION OF PROPOSAL:

Additional storey to facilitate the creation of six flats and change of use of part ground from B1 office to retail for the building to comprise of a retail unit on the ground floor and retained under croft parking, offices to first floor, and the flats on the second and newly created third floor.

 

DECISION:

Grant Permission (Subject to Legal Agreement)

 

Click on the link below to view related plans and documents for this case:

http://planpub.eppingforestdc.gov.uk/NIM.websearch/ExternalEntryPoint.aspx?SEARCH_TYPE=1&DOC_CLASS_CODE=PL&FOLDER1_REF=648775

 

CONDITIONS

1

The development hereby permitted shall be begun before the expiration of three years from the date of this permission.

 

2

The development hereby permitted shall be carried out and retained strictly in accordance with the following approved plans: Location plan, 20102; 001, 002, 003, 004, 005, 101, 102, 103, 104/A, 105/A, 106/A, 107/A, 108/A, 109/A, 110/A, 111/A.

 

3

The materials to be used in the construction of the external surfaces of the development hereby permitted shall match in colour, style, bonding & texture those shown on plan numbers: 20102; 001, 002, 003, 004, 005, 101, 102, 103, 104/A, 105/A, 106/A, 107/A, 108/A, 109/A, 110/A, 111/A.

 

4

Wheel washing or other cleaning facilities for vehicles leaving the site during construction works shall be installed and utilised to clean vehicles immediately before leaving the site. Any mud or other material deposited on nearby roads as a result of the development shall be removed.

 

5

No deliveries, external running of plant and equipment or demolition and construction works, other than internal works not audible outside the site boundary, shall take place on the site other than between the hours of 07:30 to 18:00 on Monday to Friday and 08:00 to 13:00 on Saturday and not at all on Sundays, Public or Bank Holidays without the prior written permission of the Local Planning Authority.

 

6

Prior to any above groundworks, details and location of the parking spaces (including garages) equipped with active and/or passive Electric Vehicle Charging Point(s) shall have been submitted to and approved in writing with the Local Planning Authority (LPA), unless otherwise agreed in writing with the LPA. The installation of EVCP shall be completed in accordance with the approved details and made operational prior to first occupation. The details shall include: 

 

- Location of active and passive charging infrastructure; 

- Specification of charging equipment; and

- Operation/management strategy. The council will expect that a management plan for the charging points is set out clearly. This will address: 

a) Which parking bays will have active and/or passive charging provision, including disabled parking bays; 

b) How charging point usage will be charged amongst users; 

c) The process and the triggers for identifying when additional passive charging points will become activated; and

d) Electricity supply availability. The electricity supply should be already confirmed by the Network Provider so that the supply does not need to be upgraded at a later date. 

 

7

Prior to first occupation of the development, measures shall be incorporated within the development to ensure a water efficiency standard of 110 litres (or less) per person per day.

 

8

No development shall take place, including any works of demolition, until a Construction Method Statement has been submitted to, and approved in writing by, the Local Planning Authority. The approved Statement shall be adhered to throughout the construction period. The Statement shall provide for:

 

1. The parking of vehicles of site operatives and visitors

2. Loading and unloading of plant and materials

3. Storage of plant and materials used in constructing the development

4. The erection and maintenance of security hoarding including decorative displays and facilities for public viewing, where appropriate

5. Measures to control the emission of dust and dirt during construction, including wheel washing.

6. A scheme for recycling/disposing of waste resulting from demolition and construction works.

 

9

The proposed use of this site has been identified as being particularly vulnerable if land contamination is present, despite no specific former potentially contaminating uses having been identified for this site. Should any discoloured or odorous soils be encountered during development works or should any hazardous materials or significant quantities of non-soil forming materials be found, then all development works should be stopped, the local planning authority contacted and a scheme to investigate the risks and/or the adoption of any required remedial measures be submitted to, agreed and approved in writing by the local planning authority prior to the recommencement of development works. In such instances, following the completion of development works and prior to the first occupation of the site, sufficient information must be submitted to demonstrate that any required remedial measures were satisfactorily implemented or confirmation provided that no unexpected contamination was encountered.

 

Supporting documents: