Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To consider the provision of a crèche extension at Loughton Leisure Centre.
(1) That, given the level of ongoing subsidy required for a relatively small number of customers and the alternative new opportunities being provided by Places for People, the provision of a crèche at Loughton Leisure Centre be not supported; and
(2) That provision be made in the Capital Programme in the sum of £324,000 for 2018/19 to fund the refurbishment of the Changing Village at Loughton Leisure Centre.
Report author: Jim Nolan
Publication date: 12/12/2017
Date of decision: 07/12/2017
Decided at meeting: 07/12/2017 - Cabinet
Effective from: 21/12/2017
Accompanying Documents: