Decision Maker: Housing and Strategic Health Partnerships Portfolio Holder
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
(1) That Gracelands CMS Ltd be awarded the 1-year contract renewable annually for up to a maximum of 4-further years, for the planned block electrical testing and electrical upgrades to Council owned properties in the sum of £230,274.06 with an overall weighted price and quality score of 82.8%;
(2) That the overall value of the works be capped to the sum included in the Capital Programme identified for Electrical Rewires and Upgrades on an annual basis; and
(3) That this contract be designated as a serial contract to facilitate the annual adjustment to the tendered rates in accordance with the Royal Institution of Chartered Surveyors (RICS) BCIS ALLCOS Resource Cost Index of All Construction: All Repair and Maintenance Work #7419.
Publication date: 27/02/2019
Date of decision: 27/02/2019
Effective from: 07/03/2019
Accompanying Documents: