Agenda item

Planning Application EPF/1153/09 – Rear of 103 High Street, Ongar– Partial demolition of existing buildings, conversion and adaptation of existing business units to form 3 x 1 bedroom cottages, construction of 2 x 2 bedroom cottages, bin stores, bike stores and provision of parking spaces.

(Head of Planning and Economic Development) To consider the attached report.

Minutes:

The Committee received an application referred to it by Area Planning Subcommittee East it its meeting on 16 December 2009. The proposal had been previously been the subject of a recommendation to grant approval in October 2009 subject to the completion of a Section 106 Agreement to secure affordable housing as part of the development.

 

The applicants had now provided a financial appraisal of the scheme which concluded that the development would not be viable with the inclusion of an affordable unit. The Area Subcommittee had received this information to their meeting in March 2011 together with an offer from the applicant to make a contribution of £10,000 at which time they had referred the application to the District Development Committee.

 

The Committee’s view was that on balance the application should be granted, despite some concerns at the narrowness of the access to the site.

 

Resolved:

 

That, subject to the prior completion of an agreement under Section 106 of the Town and Country Planning Act 1990 within six months of the date of this resolution, to secure £10,000 to meet community need in the Ongar area, Planning application EPF/1153/09 at R/O 103 High Street, Ongar be granted with the following conditions:

 

(1)        The development hereby permitted must be begun not later than the expiration of three years beginning with the date of this notice.

 

(2)        Details of the types and colours of the external finishes shall be submitted for approval by the Local Planning Authority in writing prior to the commencement of the development, and the development shall be implemented in accordance with such approved details.

 

(3)        Notwithstanding the provisions of the Town and Country Planning General Permitted Development Order 1995 as amended (or any other order revoking, further amending or re-enacting that order) no development generally permitted by virtue of Part 1 Classes (A-H) and Part 2 Class A shall be undertaken without the prior written permission of the Local Planning Authority.

 

(4)        The development, including site clearance, must not commence until a scheme of landscaping and a statement of the methods of its implementation have been submitted to the Local Planning Authority and approved in writing. The approved scheme shall be implemented within the first planting season following the completion of the development hereby approved.

 

The scheme must include details of the proposed planting including a plan, details of species, stock sizes and numbers/densities where appropriate, and include a timetable for its implementation.  If any plant dies, becomes diseased or fails to thrive within a period of 5 years from the date of planting, or is removed, uprooted or destroyed, it must be replaced by another plant of the same kind and size and at the same place, unless the Local Planning Authority agrees to a variation beforehand, and in writing.

 

The statement must include details of all the means by which successful establishment of the scheme will be ensured, including preparation of the planting area, planting methods, watering, weeding, mulching, use of stakes and ties, plant protection and aftercare.  It must also include details of the supervision of the planting and liaison with the Local Planning Authority.

 

The landscaping must be carried out in accordance with the agreed scheme and statement, unless the Local Planning Authority has given its prior written consent to any variation.

 

(5)        The parking area shown on the approved plan shall be provided prior to the first occupation of the development and shall be retained free of obstruction for the parking of residents and visitors vehicles.

 

(6)        All construction/demolition works and ancillary operations (which includes deliveries and other commercial vehicles to and from the site) which are audible at the boundary of noise sensitive premises, shall only take place between the hours of 07.30 to 18.30 Monday to Friday and 08.00 to 13.00 hours on Saturday, and at no time during Sundays and Public/Bank Holidays unless otherwise agreed in writing by the Local Planning Authority.

 

(7)        Prior to commencement of development, including demolition or site clearance works, a phased contaminated land investigation shall be undertaken to assess the presence of contaminants at the site in accordance with an agreed protocol as below.  Should any contaminants be found in unacceptable concentrations, appropriate remediation works shall be carried out and a scheme for any necessary maintenance works adopted.

 

Prior to carrying out a phase 1 preliminary investigation, a protocol for the investigation shall be agreed in writing with the Local Planning Authority and the completed phase 1 investigation shall be submitted to the Local Planning Authority upon completion for approval.

 

Should a phase 2 main site investigation and risk assessment be necessary, a protocol for this investigation shall be submitted to and approved by the Local Planning Authority before commencing the study and the completed phase 2 investigation with remediation proposals shall be submitted to and approved by the Local Planning Authority prior to any remediation works being carried out.

 

Following remediation, a completion report and any necessary maintenance programme shall be submitted to the Local Planning Authority for approval prior to first occupation of the completed development.

 

(8)        No demolition/ conversion or preliminary groundworks of any kind shall take place until the applicant has secured the implementation of a programme of archaeological work in accordance with a written scheme of investigation which has been submitted by the applicant and approved by the local planning authority.

 

(9)        Additional drawings that show details of proposed new windows, doors, rooflights, eaves, rainwater goods, verges, fascias, cills, structural openings and junctions with the existing building, by section and elevation at scales between 1:20 and 1:1 as appropriate, shall be submitted to and approved by the LPA in writing prior to the commencement of any works.

 

(10)      Notwithstanding the requirements of condition 9, the windows to the newbuild cottages shall be recessed into the wall and shall be timber sashes including "horns" in Victorian style.

 