Agenda item

Planning Application EPF/0247/09 – Land adjacent to Copperfield Lodge, Hainault Road, Chigwell – Erection of new five bedroom house with basement and integral garage

(Director of Planning and Economic Development) To consider the attached report.

Minutes:

The Committee gave further consideration to an application for the erection of a new five bedroomed house on land next to Victory Hall in Hainault Road, Chigwell. The Committee had last considered the matter at their meeting on 5 April 2011 (minute 38 refers) when they had given an extension of time for the completion of an Agreement under Section 106 of the Town and Country Planning Act 1990 to secure the provision of additional car parking for the adjacent Victory Hall and the transfer of associated land to the Council.

 

The Committee noted that, as yet, no legal agreement had been completed due to problems in its execution and the timescale for the completion for the Council to accept the car parking given the existing lease of Victory Hall.

 

The Committee heard from the Applicants Agent.

 

Following negotiations with the Applicant’s Agent an alternative planning obligation had been proposed, whereby the Applicant would agree to contribute the land and the cost of constructing the car parking.  Accordingly, if the Council considered it appropriate at a later date, it could construct the parking at no additional public cost.  However, if at that time it was considered that there would be a more positive community benefit which could be secured through the provision of an alternative community benefit, either within the Victory Hall site or elsewhere within the locality, then the contribution could have been put towards that purpose. 

 

The Committee, however, were of the view that within the original special circumstances of the development, the provision of the new spaces was a key factor and resolved that the contribution made by the developer should be to provide the parking spaces originally envisaged by the approval given on 9 June 2009 and for other purpose.

 

            Resolved:

 

That, subject to the completion of a Section 106 legal agreement within six calendar months to secure:

 

(a)        The transfer of land adjacent to the Victory Hall site to Epping Forest District Council, at no cost;

 

(b)        The payment of the sum of £31,400 to Epping Forest District Council to be spent on the construction of parking bays as envisaged by the original planning consent EPF/1767/09; and

 

(c)        The payment (sum to be confirmed) of the Council’s costs incurred in maintaining the site for a period of five years;

 

planning application EPF/0247/09 be granted subject to the conditions previously imposed by the Committee at their meeting on 9 June 2009 namely:

 

(1)        The development hereby permitted must be begun not later than the expiration of three years beginning with the date of this notice.

 

Reason: To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended).

 

(2)        Details of the types and colours of the external finishes shall be submitted for approval by the Local Planning Authority in writing prior to the commencement of the development, and the development shall be implemented in accordance with such approved details.

 

 Reason:- To ensure a satisfactory appearance in the interests of visual amenity.

 

(3)        The development, including site clearance, must not commence until a scheme of landscaping and a statement of the methods of its implementation have been submitted to the Local Planning Authority and approved in writing. The approved scheme shall be implemented within the first planting season following the completion of the development hereby approved. The scheme must include details of the proposed planting including a plan, details of species, stock sizes and numbers/densities where appropriate, and include a timetable for its implementation. If any plant dies, becomes diseased or fails to thrive within a period of 5 years from the date of planting, or is removed, uprooted or destroyed, it must be replaced by another plant of the same kind and size and at the same place, unless the Local Planning Authority agrees to a variation beforehand, and in writing. The statement must include details of all the means by which successful establishment of the scheme will be ensured, including preparation of the planting area, planting methods, watering, weeding, mulching, use of stakes and ties, plant protection and aftercare. It must also include details of the supervision of the planting and liaison with the Local Planning Authority  The landscaping must be carried out in accordance with the agreed scheme and statement, unless the Local Planning Authority has given its prior written consent to any variation.

 

Reason:- To comply with the duties indicated in Section 197 of the Town and Country Planning Act 1990 so as to ensure that the details of the development of the landscaping are complementary, and to ensure a satisfactory appearance to the development.

 

(4)        All material excavated from the below ground works hereby approved shall be removed from the site unless otherwise agreed in writing by the Local Planning Authority.

 

Reason: In order to control any alteration to levels or spreading of material not indicated on the approved plans in the interests of amenity and the protection of natural features.

 

(5)        Prior to commencement of development, including demolition or site clearance works, a phased contaminated land investigation shall be undertaken to assess the presence of contaminants at the site in accordance with an agreed protocol as below. Should any contaminants be found in unacceptable concentrations, appropriate remediation works shall be carried out and a scheme for any necessary maintenance works adopted. Prior to carrying out a phase 1 preliminary investigation, a protocol for the investigation shall be agreed in writing with the Local Planning Authority and the completed phase 1 investigation shall be submitted to the Local Planning Authority upon completion for approval. Should a phase 2 main site investigation and risk assessment be necessary, a protocol for this investigation shall be submitted to and approved by the Local Planning Authority before commencing the study and the completed phase 2 investigation with remediation proposals shall be submitted to and approved by the Local Planning Authority prior to any remediation works being carried out. Following remediation, a completion report and any necessary maintenance programme shall be submitted to the Local Planning Authority for approval prior to first occupation of the completed development.

 

Reason:- Since the site has been identified as being potentially contaminated and to protect human health, the environment, surface water, groundwater and the amenity of the area.

 

(6)        No demolition or preliminary ground works of any kind shall take place until the applicant has secured the implementation of a programme of archaeological work in accordance with a written scheme of investigation which has been submitted to and approved by the local planning authority.

 

Reason: To protect any material of archaeological interest of the site, due to the location of the proposed development on the site of a Roman Road.

 

(7)        Prior to commencement of development, details of levels shall be submitted to and approved by the Local Planning Authority showing the levels of the site prior to development and the proposed levels of all ground floor slabs of buildings, roadways and accessways and landscaped areas. The development shall be carried out in accordance with those approved details.

 

Reason: To enable appropriate consideration to be given to the impact of the intended development upon adjacent properties.

 

(8)        Notwithstanding the provisions of the Town and Country Planning General Permitted Development Order 1995 as amended (or any other order revoking, further amending or re-enacting that order) no development generally permitted by virtue of Part 1, Classes A, B, E shall be undertaken without the prior written permission of the Local Planning Authority.

 

Reason:- The specific circumstances of this site warrant the Local Planning Authority having control over any further development.

 

(9)        Prior to the commencement of development details of screen walls, fences or such similar structures shall be agreed in writing by the Local Planning Authority, and shall be erected before the occupation of any of the dwellings hereby approved and maintained in the agreed positions.

 

Reason:- In the interests of visual amenity.

 

(10)      Prior to the commencement of the development details of the proposed surface materials for the access shall be submitted to and approved in writing by the Local Planning Authority. The agreed surface treatment shall be completed prior to the first occupation of the development.

 

Reason:- To ensure that a satisfactory surface treatment is provided in the interests of highway safety and visual amenity.

 

(11)      Prior to the first occupation of the development hereby permitted there shall be no obstruction within a parallel band visibility spay 2.4m wide as measured from the back edge of the carriageway across the entire site frontage. This area shall be retained free from any obstruction in perpetuity.

 

Reason: To provide adequate inter-visibility between users of the access and the existing public highway for the safety and convenience of users of the highway and of the access in accordance with policy ST4 of the Adopted Local Plan and Alterations.

 

(12)      Any gates provided at the vehicular access shall only open inwards and shall be set back a minimum of 4.8 metres from the nearside edge of the carriageway.

 

Reason: To enable vehicles using the access to stand clear of the carriageway/footway whilst gates are being opened and closed in accordance with policy ST4 of the Adopted Local Plan and Alterations.

 

(13)      Prior to the first occupation of the development permitted the existing crossover shall be removed and the footpath resurfaced and the kerb reinstated for use as approved in writing by the local planning authority.

 

Reason: In the interests of highway safety in accordance with policy ST4 of the Adopted Local Plan and Alterations.

 

(14)      Wheel washing or other cleaning facilities for vehicles leaving the site during construction works shall be installed in accordance with details which shall be submitted to and agreed in writing by the Local Planning Authority and these facilities installed prior to the commencement of any building works on site, and shall be used to clean vehicles leaving the site.

 

Reason:- To avoid the deposit of material on the public highway in the interests of highway safety.

Supporting documents: