DESCRIPTION OF PROPOSAL:

Proposed new detached one-bedroom dwelling and associated works. (Revised application to EPF/3066/18)

 

DECISION:

Grant Permission (With Conditions) subject to S106 Legal Agreement

 

Click on the link below to view related plans and documents for this case:

http://planpub.eppingforestdc.gov.uk/NIM.websearch/ExternalEntryPoint.aspx?SEARCH_TYPE=1&DOC_CLASS_CODE=PL&FOLDER1_REF=624316

 

 

CONDITIONS

1

The development hereby permitted must be begun not later than the expiration of three years beginning with the date of this notice.

 

2

The development hereby permitted will be completed strictly in accordance with the approved drawings numbers: Site Location Plan and B1.1

 

3

No construction works above ground level shall have taken place until documentary and photographic details of the types and colours of the external finishes have been submitted to and approved by the Local Planning Authority, in writing, prior to the commencement of the development. The development shall be implemented in accordance with such approved details.

 

4

Prior to first occupation of the development, measures shall be incorporated within the development to ensure a water efficiency standard of 110 litres (or less) per person per day.

 

5

Prior to preliminary ground works taking place, details of surface water disposal shall be submitted to and approved in writing by the Local Planning Authority. The development shall be implemented in accordance with such agreed details.

 

6

Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, as amended, (or any other order revoking, further amending or re-enacting that Order) no development generally permitted by virtue of Class A, B, C, D or E of Part 1 of Schedule 2 to the Order, shall be undertaken without the prior written permission of the Local Planning Authority.

 

7

Prior to any above ground works, full details of both hard and soft landscape works (including tree planting) and implementation programme (linked to the development schedule) shall be submitted to and approved in writing by the Local Planning Authority. These works shall be carried out as approved. The hard landscaping details shall include, as appropriate, and in addition to details of existing features to be retained: proposed finished levels or contours; means of enclosure; car parking layouts; other minor artefacts and structures, including signs and lighting and functional services above and below ground. The details of soft landscape works shall include plans for planting or establishment by any means and full written specifications and schedules of plants, including species, plant sizes and proposed numbers /densities where appropriate. If within a period of five years from the date of the planting or establishment of any tree, or shrub or plant, that tree, shrub, or plant or any replacement is removed, uprooted or destroyed or dies or becomes seriously damaged or defective another tree or shrub, or plant of the same species and size as that originally planted shall be planted at the same place, unless the Local Planning Authority gives its written consent to any variation.

 

8

No ground works shall take place until details of levels have been submitted to and approved by the Local Planning Authority showing cross-sections and elevations of the levels of the site prior to development and the proposed levels of all ground floor slabs of buildings, roadways and accessways and landscaped areas. The development shall be carried out in accordance with those approved details.

 

9

No development shall commence until an assessment of the risks posed by any contamination, carried out in accordance with British Standard BS 10175: Investigation of potentially contaminated sites - Code of Practice and the Environment Agency's Model Procedures for the Management of Land Contamination (CLR 11) (or equivalent British Standard and Model Procedures if replaced), shall have been submitted to and approved in writing by the local planning authority. If any contamination is found, a report specifying the measures to be taken, including the timescale, to remediate the site to render it suitable for the approved development shall be submitted to and approved in writing by the local planning authority. The site shall be remediated in accordance with the approved measures and timescale and a verification report shall be submitted to and approved in writing by the local planning authority. If, during the course of development, any contamination is found which has not been previously identified, work shall be suspended and additional measures for its remediation shall be submitted to and approved in writing by the local planning authority. The remediation of the site shall incorporate the approved additional measures and a verification report for all the remediation works shall be submitted to the local planning authority within 21 days of the report being completed and approved in writing by the local planning authority.

 

 

10

Following completion of the measures identified in the approved remediation scheme, and prior to the first use or occupation of the development, a verification report that demonstrates the effectiveness of the remediation carried out must be produced together with any necessary monitoring and maintenance programme and copies of any waste transfer notes relating to exported and imported soils shall be submitted to the Local Planning Authority for approval. The approved monitoring and maintenance programme shall be implemented. 

 

11

In the event that any evidence of potential contamination is found at any time when carrying out the approved development that was not previously identified in the Phase 2 report, work shall be suspended and additional measures for its remediation shall be submitted to and approved in writing by the local planning authority. The remediation of the site shall incorporate the approved additional measures and a verification report for all the remediation works shall be submitted to the local planning authority within 21 days of the report being completed and approved in writing by the local planning authority.

 

12

All construction/demolition works and ancillary operations, including vehicle movement on site which are audible at the boundary of noise sensitive premises, shall only take place between the hours of 07.30 to 18.30 Monday to Friday and 08.00 to 13.00 hours on Saturday, and at no time during Sundays and Public/Bank Holidays unless otherwise agreed in writing by the Local Planning Authority.

 

13

Prior to first occupation of the development, a scheme to enhance the ecological value of the site shall be submitted to and agreed in writing by the Local Planning Authority. The ecological value shall be quantified using the Biodiversity Impact Assessment Calculator (BIAC) where appropriate. The scheme shall be implemented in full prior to the occupation of the development hereby approved.

 

 

14

Prior to preliminary ground works taking place, details of surface water disposal shall be submitted to and approved in writing by the Local Planning Authority. The development shall be implemented in accordance with such agreed details.

 

15

All bedrooms within the development hereby approved shall be provided with sufficient double glazing and acoustically treated trickle ventilators, or other means of ventilation, that will provide adequate ventilation with the windows closed, to ensure that the occupiers are provided with reasonable resting/sleeping conditions with reference to British Standard BS8233:2014 - Sound insulation and noise reduction for buildings - Code of Practice (or such other standard which may supersede it from time to time).

 

16

Details of the double glazing and acoustically treated trickle ventilators, or other means of ventilation, referred to in the above Condition 15 shall be submitted to and agreed in writing by the Local Planning Authority and installed before any of the proposed residential development is occupied. 

 

17

Full details of any acoustic barriers shall be submitted to, and agreed in writing with the Local Planning Authority, and installed before any of the proposed residential development is occupied, to ensure that the occupiers are provided with reasonable use of external amenity space, as recommended by British Standard BS8233:2014 - Sound insulation and noise reduction for buildings - Code of Practice (or such other standard which may supersede it from time to time).

 

18        

Prior to first occupation of the development, the Developer shall be responsible for

the provision, implementation and distribution of a Residential Travel Information

Pack for sustainable transport, approved by Essex County Council, to include six

one day travel vouchers for use with the relevant local public transport operator.

These packs (including tickets) are to be provided by the Developer to each

dwelling free of charge.

 