Agenda item

Planning Application - EPF/2122/20 11 Kendal Avenue, Epping CM16 4PW

To consider the attached report for a new detached four bedroom house to the rear of the site, including a raised driveway and a detached garage.

Minutes:

Application Ref:

EPF/2122/20

Application Type:

Full planning permission

Case Officer:

Cuma Ahmet

Site Address:

11 Kendal Avenue

Epping

CM16 4PW

Proposal:

A new detached four bedroom house to the rear of the site, including a raised driveway and a detached garage.

Ward:

Epping Hemnall

Parish:

Epping

View Plans:

https://eppingforestdcpr.force.com/pr/s/planning-application/a0h8d000000Nwsd

 

Decision:

Approve with Conditions

 

Conditions: (16)

 

 

1

 

The development hereby permitted shall begin not later than three years from the date of this decision.


Reason: To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended).

 

 

2

 

The development hereby permitted shall be carried out and retained strictly in accordance with the following approved plans:

 

100/REV B

101/REV F

102/REV C

17118/P001/REV G

17118/P002

 

Reason: For the avoidance of doubt and to ensure the proposal is built in accordance with the approved plans.

 

 

3

 

Samples of the types and details of colours of all the external finishes shall be submitted for approval in writing by the Local Planning Authority prior to the commencement of the development, and the development shall be implemented in accordance with such approved detail.

 

Reason: To ensure the proposed works preserve the special architectural and historic interest of the building, in accordance with policy DBE1 and DBE3 of the adopted Local Plan and Alterations 1998 & 2006, policy DM9 and DM10 of the Local Plan Submission Version 2017, and the NPPF.

 

 

4

No preliminary ground works shall take place until a flood risk assessment and management and maintenance plan shall be submitted to and approved by the Local Planning Authority prior to commencement of development. The assessment shall include calculations of increased run-off and associated volume of storm detention using WinDes or other similar best practice tools. The approved measures shall be carried out prior to the substantial completion of the development and shall be adequately maintained in accordance with the management and maintenance plan.

 

Reason: The development is of a size where it is likely to result in increased surface water run-off, in accordance with policy U2B of the adopted Local Plan and Alterations 1998 & 2006, and policy T1 of the Local Plan Submission Version 2017, and the NPPF.

 

 

5

 

Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015 (as amended) (or any other order revoking and re-enacting that order) no development permitted by virtue of Classes, A B and E of Part 1 to Schedule 2 shall be undertaken, without the prior written agreement of the Local Planning Authority. 

 

Reason: The ensure further consideration is given with regards to the effect on the character and appearance of the area and living conditions on adjoining properties, in accordance with policy DBE9 of the adopted Local Plan 1998 & 2006, policies DM9 and DM10 of the Local Plan Submission Version 2017, and the NPPF.

 

 

6

 

Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any order revoking and re-enacting that Order with or without modification), no windows other than those expressly authorised by this permission shall be constructed on any elevation, without the prior written agreement of the Local Planning Authority.

 

Reason: The ensure further consideration is given with regards to the effect on the living conditions on adjoining properties, in accordance with policy DBE9 of the adopted Local Plan 1998 & 2006, policies DM9 and DM10 of the Local Plan Submission Version 2017, and the NPPF.

 

 

7

 

If any tree, shrub or hedge shown to be retained in the submitted Arboricultural reports is removed, uprooted or destroyed, dies, or becomes severely damaged or diseased during development activities or within 3 years of the completion of the development, another tree, shrub or hedge of the same size and species shall be planted within 3 months at the same place. If within a period of five years from the date of planting any replacement tree, shrub or hedge is removed, uprooted or destroyed, or dies or becomes seriously damaged or defective another tree, shrub or hedge of the same species and size as that originally planted shall, within 3 months, be planted at the same place.

 

Reason: To comply with the duties indicated in Section 197 of the Town and Country Planning Act 1990 as well as to safeguard the amenity of the existing trees, shrubs or hedges and to ensure a satisfactory appearance to the development, in accordance with policies LL10 and LL11 of the adopted Local Plan and Alterations 1998 & 2006, and policies DM3 and DM5 of the Local Plan Submission Version 2017, and the NPPF.

 

 

8

Prior to any above ground works, full details of both hard and soft landscape works (including tree planting) and implementation programme (linked to the development schedule) shall be submitted to and approved in writing by the Local Planning Authority. All hard and soft landscape works shall be carried out in accordance with the approved details. The works shall be carried out prior to the occupation of the building or completion of the development, whichever is the sooner. The hard landscaping details shall include, as appropriate, and in addition to details of existing features to be retained: proposed finished levels or contours; means of enclosure; car parking layouts; other minor artefacts and structures, including signs and lighting and functional services above and below ground. The details of soft landscape works shall include plans for planting or establishment by any means and full written specifications and schedules of plants, including species, plant sizes and proposed numbers /densities where appropriate. If within a period of five years from the date of the planting or establishment of any tree, or shrub or plant, that tree, shrub, or plant or any replacement is removed, uprooted or destroyed or dies or becomes seriously damaged or defective another tree or shrub, or plant of the same species and size as that originally planted shall be planted at the same place.

 

Reason: To comply with the duties indicated in Section 197 of the Town and Country Planning Act 1990 so as to ensure that the details of the development of the landscaping are complementary, and to ensure a satisfactory appearance to the development, in accordance with policies CP2 and LL11 of the adopted Local Plan and Alterations 1998 & 2006, policies DM3 and DM5 of the Local Plan Submission Version 2017, and the NPPF.

 

 

9

 

No development, including works of demolition or site clearance, shall take place until a Tree Protection Plan, Arboricultural Method Statement and site monitoring schedule in accordance with BS:5837:2012 (Trees in relation to design, demolition and construction - Recommendations) has been submitted to the Local Planning Authority and approved in writing. The development shall be carried out only in accordance with the approved documents.

 

Reason: To comply with the duties indicated in Section 197 of the Town and Country Planning Act 1990, and to enable full and proper consideration be given to the impact of the proposed development on existing trees / hedges, so as to safeguard and enhance the visual amenities of the area and to ensure a satisfactory appearance to the development in accordance with policy LL10 of the adopted Local Plan and Alterations 1998 & 2006, policies DM3 and DM5 of the Local Plan Submission Version 2017, and the NPPF.

 

 

10

 

No services shall be installed within the root protection area of any retained trees on or adjacent to the site unless the Local Planning Authority gives its prior written approval.

 

Reason: To comply with the duties indicated in Section 197 of the Town & Country Planning Act 1990 so as to ensure that the amenity value of tree(s) are safeguarded in accordance with the guidance contained within the National Planning Policy Framework, policy

LL10 of the adopted Local Plan and Alterations, and policies DM 3 and DM 5 of the Epping

Forest District Council Local Plan Submission Version 2017.”

 

 

11

Prior to first occupation of the development, measures shall be incorporated within the development to ensure a water efficiency standard of 110 litres (or less) per person per day.

 

Reason: The District is classed as being in an area of severe water stress and the reduction of water use is therefore required in the interests of sustainability and in accordance with policy CP2 of the adopted Local Plan and Alterations 1998 & 2006, policy DM19 of the Local Plan Submission Version 2017, and the NPPF.

 

 

12

 

Prior to any above groundworks, details and location of the parking spaces (including garages) equipped with active Electric Vehicle Charging Point(s) shall have been submitted to and approved in writing with the Local Planning Authority (LPA), unless otherwise agreed in writing with the LPA. The installation of EVCP shall be completed in accordance with the approved details and made operational prior to first occupation. The details must include details as follows: 

 

- Location of active charging infrastructure; and

- Specification of charging equipment to be used.

 

Reason: To ensure the development contributes to supporting the Council towards a low carbon future and the wider aims and objectives for reducing car-led air pollution in regard to the EFSAC, in accordance with policy CP1 of the adopted Local Plan 1998 & 2006, Policies T1 & DM22 of the Local Plan Submission Version 2017, and the NPPF.

 

 

13

 

No deliveries, external running of plant and equipment or demolition and construction works, other than internal works not audible outside the site boundary, shall take place on the site other than between the hours of 07:30 to 18:00 on Monday to Friday and 08:00 to 13:00 on Saturday and not at all on Sundays, Public or Bank Holidays.

 

Reason: To ensure that the proposed construction work does not cause undue nuisance and disturbance to neighbouring properties at unreasonable hours and in accordance with policies RP5A and DBE9 of the adopted Local Plan 1998 & 2006, and policies DM9 and DM 21 of the Local Plan Submission Version 2017, and the NPPF.

 

 

14

 

Wheel washing or other cleaning facilities for vehicles leaving the site during construction works shall be installed and utilised to clean vehicles immediately before leaving the site. Any mud or other material deposited on nearby roads as a result of the development shall be removed.

 

Reason: To avoid the deposit of material on the public highway in the interests of highway safety, in accordance with policy ST4 of the adopted Local Plan and Alterations 1998 & 2006, policy T1 of the Local Plan Submission Version 2017, and the NPPF.

 

 

15

 

The proposed use of this site has been identified as being particularly vulnerable if land contamination is present, despite no specific former potentially contaminating uses having been identified for this site. Should any discoloured or odorous soils be encountered during development works or should any hazardous materials or significant quantities of non-soil forming materials be found, then all development works should be stopped and an assessment of the risks posed by any contamination, carried out in accordance with British Standard BS 10175: Investigation of potentially contaminated sites - Code of Practice and the Environment Agency's Model Procedures for the Management of Land Contamination (CLR 11) (or equivalent British Standard and Model Procedures if replaced) shall be undertaken. If any contamination is found then the site shall be remediated. The remediation scheme shall be sufficiently detailed and thorough to ensure that upon completion the site will not qualify as contaminated land under Part IIA of the Environmental Protection Act 1990 in relation to its intended use.

 

Reason: It is the responsibility of the developer to ensure the safe development of the site and to carry out any appropriate land contamination investigation and remediation works. The condition is to ensure the risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors, in accordance with policy RP4 of the adopted Local Plan and Alterations, and policy DM21 of the Local Plan Submission Version 2017, and the NPPF.

 

 

16

 

Prior to any above groundworks, a strategy to facilitate super-fast broadband for future occupants of the site shall have been submitted to and approved in writing by the Local Planning Authority (LPA). The strategy shall seek to ensure that upon occupation of a dwelling, either a landline or ducting to facilitate the provision of a broadband service to that dwelling from a site-wide network, is in place and provided as part of the initial highway works and in the construction of frontage thresholds to dwellings that abut the highway, unless evidence is put forward and agreed in writing by the LPA that technological advances for the provision of a broadband service for the majority of potential customers will no longer necessitate below ground infrastructure. The development of the site shall be carried out in accordance with the approved strategy.

 

Reason: To ensure the development contributes to supporting improved digital connectivity throughout the District and supports the wider aims and objectives for reducing car-led air pollution, improving the health and wellbeing of residents and visitors including the EFSAC, in accordance with policy CP1 of the adopted Local Plan 1998 & 2006, Policies D5, DM2, DM9, DM10 & DM22 of the Local Plan Submission Version 2017, and the NPPF.

 

 

Informatives: (4)

 

 

17

 

The Local Planning Authority has acted positively and proactively in determining this application by assessing the proposal against all material considerations, including planning policies and any representations that may have been received and subsequently determining to grant planning permission in accordance with the presumption in favour of sustainable development, as set out within the National Planning Policy Framework.

 

 

18

 

All work within or affecting the highway is to be laid out and constructed by prior arrangement with, and to the requirements and satisfaction of, the Highway Authority, details to be agreed before the commencement of works. The applicants should be advised to contact the Development Management Team by email at development.management@essexhighways.org or by post to:SMO3 - Essex Highways, Unit 36, Childerditch Industrial Park, Childerditch Hall Drive, Brentwood, Essex, CM13 3HD.

 

 

19

 

Note: Under the Land Drainage Byelaws of this Council, Land Drainage Consent is also required before any work commences. Please contact the Land Drainage team on 01992 564000 for application forms. The grant of planning permission does not imply the automatic grant of Land Drainage Consent.

 

 

20

 

This permission is also subject to conditions and/or covenants of an accompanying Section 106 Agreement.

 

 

 