Find information about decisions that have been taken. Search by date, decision maker or decision status.
Decision Maker: Council Housebuilding Cabinet Committee
Made at meeting: 19/12/2019 - Council Housebuilding Cabinet Committee
Decision published: 23/12/2019
Effective from: 19/12/2019
Decision:
That the contents of this Progress Report on Phases 4 to 6 of the Council House Building Programme be noted and presented to the Cabinet in line with the Terms of Reference of the Council Housebuilding Cabinet Committee.
Decision Maker: Council Housebuilding Cabinet Committee
Made at meeting: 19/12/2019 - Council Housebuilding Cabinet Committee
Decision published: 23/12/2019
Effective from: 19/12/2019
Decision:
(1) That, TSG Building Services PLC be awarded the contract to undertake the construction of 5 properties, Chequers Road and Bushfields, Loughton in the sum of £1,365,481 together with the proposed construction period of 48 weeks.
(2) That, TSG Building Services PLC be awarded the contract to undertake the construction of 3 properties, Chester Road, Loughton in the sum of £747,395 together with the proposed construction period of 34 weeks.
(3) That TSG Building service PLC therefore recommend acceptance of the tender submitted by TSG Building Services PLC be awarded the contract to undertake the construction of 6 properties, Queensway, Ongar & Millfield, Higher Ongar in the sum of £1,372,925.